Greensburg Project

IDL Classrooms in Temporary Facility

 

 

Step / Stage

Description

Completion Date

Status

Equipment Ordered

Classroom replacement equipment

 

 

ATM Service Installed

AT&T installed T1 lines for IDL & waiting for electrical service to test

 

holding for test

Temporary Facility Installed

Pod on site. Brown building north side high school area.

 

in progress

Electrical Service

Electrical service to be brought up together

 

in progress

Equipment Cabinets installed

Used rack cabinets installed; previously stored at Mullinville

23 July 07

installed

Test rack equipment

Test w/ NOC the codecs, switches, router

 

holding for test

Install Classroom equipment

Cytek to complete installation

 

on order

Permanent Facility Construction

 

Summer 2010

 

Relocate Cabinets

 

Summer 2010

 

Relocate Classrooms

 

Summer 2010